So where is the asphalt berm? Where’s the water treatment system? Surface water has intentionally been diverted away from any filtration system. Where’s the evidence the sumps were excavated, cleaned and lined? The removal of the “wood pile” aka berm was simply moved from one location to another.

Feb. 2/24. Concrete blocks by upper green barge with runoff flowing down towards filtration system.
Feb. 12/24 Concrete blocks removed.
Mar. 28/24 Trench dug diverting runoff towards soil and ocean.
Mar. 29/24
Mar. 30/24 Completed filling in and diverting runoff.
Dec. 31/24 No asphalt berm.
So called “removal of wood pile” simply moved from one location on DWR property to another.